During the Tuesday, June 5, Northern Wells school board meeting, Kari Vilamaa of the architectural firm Barton-Coe-Vilamaa presented the following timeline to complete the $14.9 million high school renovation.
Already done:
Already done:
- Group visit May 15 to Carroll High School, Whitko High School, Adams Central
- Meeting on May 21 with architects, bond counsel and financial adviser.
- Listening session on May 29 with staff.
- Meeting on May 30 to discuss food service.
- Meeting on May 31 to discuss HVAC system options.
- Meeting on June 4 with leadership group to begin design process.
- Meeting on June 5 with electric utility to discuss transformer.
Activities in June
- Develop organization concepts for remodel.
- Continue weekly design meetings with leadership group.
- Compile data and begin basic analysis/design of HVAC system.
- Develop preliminary design for kitchen.
- Begin discussion about technology.
- Review construction budget.
Design work will continue through July, August, September and October, Vilamaa said. Learn more in the Wednesday, June 6, News-Banner.