Architect presents timeline to renovate Norwell High School

During the Tuesday, June 5, Northern Wells school board meeting, Kari Vilamaa of the architectural firm Barton-Coe-Vilamaa presented the following timeline to complete the $14.9 million high school renovation.

Already done:
  • Group visit May 15 to Carroll High School, Whitko High School, Adams Central
  • Meeting on May 21 with architects, bond counsel and financial adviser.
  • Listening session on May 29 with staff.
  • Meeting on May 30 to discuss food service.
  • Meeting on May 31 to discuss HVAC system options.
  • Meeting on June 4 with leadership group to begin design process.
  • Meeting on June 5 with electric utility to discuss transformer.

Activities in June

  • Develop organization concepts for remodel.
  • Continue weekly design meetings with leadership group.
  • Compile data and begin basic analysis/design of HVAC system.
  • Develop preliminary design for kitchen.
  • Begin discussion about technology.
  • Review construction budget.

Design work will continue through July, August, September and October, Vilamaa said. Learn more in the Wednesday, June 6, News-Banner.